Revenue & Expense Recognition on PO Product Receipt

(3) ShareShare
ReportReport
Posted on by 8
Has anyone encountered when using the subcontract feature in Project Operation, where the subcontract expense is used for Revenue Recognition Percentage but the Expense does not clear out of WIP when revenue recognition is ran?  Our Project uses subcontractor expenses for labor.  The subcontract labor is setup as an item (non-stock).  When we receive the PO, the receipt amount is used to calculate revenue on the fixed fee project but the amount that is recorded to WIP on the PO receipt is not expensed out of WIP to expense. 
I have the same question (0)
  • Giorgio Bonacorsi Profile Picture
    3,530 on at
    Hello,

    Interesting. Could we have some screenshots of our document entry (agreement, PO) and the voucher?
    As far as I know, revenue recognition is now based on the Subscription Billing module. Are you using this module or the previous solution (revenue recognition module). You can leverage it to handle subcontractors, the revenue is recognized based on the terms entered in the subscription agreement lines.
     
    Thank you,
    Giorgio
  • Preethi V Profile Picture
    38 on at
    Hi,
    In Project Operations, for fixed-price projects, cost recognition and revenue recognition are handled separately.
    The revenue recognition process uses project costs to calculate the percentage of completion, but it does not necessarily mean that the related subcontract WIP will automatically be relieved to expense during the same process.

    Could you share screenshots of:

    Project group setup
    Cost and revenue profile
    PO receipt voucher
    Revenue recognition voucher
     
    This would help determine whether the issue is related to standard project accounting setup or a specific subcontract posting scenario.
     
    Thanks
  • CU09061354-0 Profile Picture
    8 on at
     
    We opened a ticket with Microsoft and unfortunately they said it is working as designed.  In order for Project Ops to Recognize both cost and expense, the invoices have to have been processed.  This is unfortunate because, the receipt of the PO is recognizing WIP Dollars and is being used to calculate Percent Complete Revenue Recognition but the costs aren't coming out of WIP.  At month-end, they may not have been invoiced from the vendor yet.  It is a poor design in my opinion

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Congratulations to the May Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 491 Super User 2026 Season 1

#2
Subra Profile Picture

Subra 422

#3
Martin Dráb Profile Picture

Martin Dráb 289 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans