Microsoft Dynamics NAV (Archived)

Production Order Scheduling

(0) ShareShare
ReportReport
Posted on by 574

Hi everyone. I was trying to figure out how to setup Manufacturing routing system in order to not have empty slots in our machine center calendar.
In this picture I show what am I trying to do: I would like that second (and successive) operations in a production order are not planned from the beginning of the next operation (backward planning). I rather have them filling all gaps so I have machine center all time running. I do not mind to have subassemblies all over the plant waiting for next operation.
We are using Capacity Constrained Resources for these Machine Centers.

capcitySchedule.png

*This post is locked for comments

I have the same question (0)

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > 🔒一 Microsoft Dynamics NAV (Archived)

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans