Currently our Requisition Worksheet is taking all future consumptions into account when usingthe re-order quantity.
For all our items with a Fixed Re-order quantity, we would like to have a purchase requisition at the moment the re-order point has been reach.
Ex 1.: I have 500 items A on stock today, production planned according to NAV on D+8 for 300 pieces of Item B (which consumes 300pc of item A). Re-order point = 250, re-order quantity = 500. NAV will propose today to buy for D+8 500 pc of item A. I don't want to have this proposal in my Worksheet, unless the re-order point has actually been reached…
Is it possible to set-it up in standard NAV?
many thanks
Jonathan
*This post is locked for comments
Hi Jonathan,
Please refer to the Design Details - Planning Parameters link below. Play around with the different periods, and running the req worksheet till you get the results you would like. This helped us out to as understanding whats happening with all the different settings can become pretty confusing.
docs.microsoft.com/.../design-details-planning-parameters
If this helps please mark the answer as verified.
Thanks!
-Chaz
How did you run the Calculate Plan ? If you only want to run based on today's stock, you can just put the ending date as today.
Stay up to date on forum activity by subscribing. You can also customize your in-app and email Notification settings across all subscriptions.
André Arnaud de Cal... 291,240 Super User 2024 Season 2
Martin Dráb 230,149 Most Valuable Professional
nmaenpaa 101,156