What the purpose of Project Quotation

(0) ShareShare
ReportReport
Posted on by 2,382

Hi Experts,

I am doing setup for Fixed-Price Project. I want to know what is the purpose of Project Quotation. When I created Project Quotation I linked to Project ID. What is the Purpose of linking Project ID.

If project is Fixed-Price. Where do I put agreed total project amount in Fixed-Price Project or Project Contract.

How Project Quotation value with matching with invoice.

If we use Product Configurator for Project Quotation than how to invoice for Project type Fixed Price.

I am new for Project. But I read Microsoft material.

Hoping for reply.

Thanks,

Faiz

I have the same question (0)
  • faiz7049 Profile Picture
    2,382 on at

    Hi Ludwig,

    I know you are expert in Project module. I am lookig for your reply. It does not means that no other experts available in this community. Anyone can reply.

    Thanks,

    Faiz

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Faiz,

    For a fixed price project you can use the project quotation as an internal calculation tool to see how much the project would actually cost you and what milestones you would have to negotiate with the customer to stay profitable with the project.

    It can also be used for grouping / structuring the tasks to get an idea who might be needed for executing the project; kind of pre-planning and assigning resources.

    Hope this helps.

    Best regards,

    Ludwig

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Oh. Overlooked the second part of your question.

    The totally agreed fixed price is not recorded in the project quotation but in the project or in the project contract.

    I would actually expect that you don't send out the quote to the customer but rather negotiate the fixed price and milestone payments with the customer based on your internal cost calculations for which the project contract can help.

    The project quotation can be kind of matched with the actuals if you transfer the quotation data into the project and into a budget or forecast model. Then you can do an actual cost - planned cost comparison. It does not match your invoices though.

    I don't have insights into the product configurator. Have not used it so far for AX2012 projects.

    Best regards,

    Ludwig

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 451 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 428 Super User 2025 Season 2

#3
BillurSamdancioglu Profile Picture

BillurSamdancioglu 239 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans