Hi guys,
I have a financial summary report with the following criteria per contract:
The variance column is (Actual less Budget), but the contribution margin % row should be (Contribution margin divided by Revenue) to still get an accurate %
How do I configure this in MR?
Thanks in advance!
Amanda
Hi Amanda,
In the report definition, click on the Settings tab. Then change the Calculation Priority to 'Perform column calculations first and then row'. That should give you the correct amount for the Contribution Margin % row. I tested it and got the correct amount.
Excellent! That easy... I appreciate your help Greg!
Thanks so much for the help previously, changing the settings to "Perform column calculations first then row" helped.
BUT now I have another issue.
Within the same report I want to now add a % variance against the Variance column.
My calculation in the column definition is IF C>0 THEN E/C ELSE 1.0 [C being FY20-Q3F forecast and E being the variance column]
I get the correct answer against the Contribution Margin % line, but the other percentages just doesn't show, no matter what I try.
Your help is again highly appreciated!
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our 2026 Super Stars!
We are thrilled to have these Champions in our Community!
These are the community rock stars!
Stay up to date on forum activity by subscribing.
Giorgio Bonacorsi 616
André Arnaud de Cal... 460 Super User 2026 Season 1
Syed Haris Shah 331 Super User 2026 Season 1