Change on "Budget Control Configuration"

(3) ShareShare
ReportReport
Posted on by 16
I have activated the budget control configuration, enabling the "Use only apportioned amount" feature. 
After that, I wanted to disable this feature by "Create draft" and re-activate it by un-clicking the  "Use only apportioned amount" box. 
 
 
The activating budget control configuration failed, as shown below: "The Budget control process didn't work."
 
Does anyone know how to disable this feature? or this feature cannot be disable after activated? 
 
 
Here are the current versions of our D365 product. 
Installed product version : 10.0.42 (10.0.2095.129)Installed platform version : Update66 (7.0.7452.105)
 
Categories:
I have the same question (0)
  • Zain Mehmood Profile Picture
    4,187 Most Valuable Professional on at
    Hi,
    Once "Use only apportioned amount" is enabled in Budget Control, it can be difficult to disable due to dependencies tied to budget allocations.
    To turn it off:
    1. Go to Budget control configuration, click Create draft.
    2. Uncheck "Use only apportioned amount".
    3. Make sure no apportionment rules or entries are still active.
    4. Try to reactivate.
    If it still fails, check for any invalid dimension setups or missing default values. 
     
    This belongs to finance forum, any moderator needs to place this in Finance Forum. 
     
    Thanks, 
    Zain
  • CU18041809-0 Profile Picture
    16 on at
    Thx Zain Mehmood 
     
     
    I have checked the appointment rules is empty. and still cannot update the and reacvitave the budget control .
  • Suggested answer
    Abhilash Warrier Profile Picture
    5,426 Super User 2025 Season 2 on at
    Here's a step-by-step guide to help you:
    1. Create a Draft: Go to the Budget Control Configuration page and click on Create draft.
    1. Uncheck the Feature: In the draft, uncheck the "Use only apportioned amount" box.

     
    1. Validate Dimensions: Verify that all financial dimensions and default values are correctly set up. Invalid dimension setups can cause activation failures.
    2. Reactivate the Configuration: Attempt to reactivate the updated configuration and wait for few seconds & refresh the page.
    I have tried the scenario & it was working.

    If this helped, please mark it as "Verified" for others facing the same issue
    Keep in mind that it is possible to mark more than one answer as verified.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 451 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 428 Super User 2025 Season 2

#3
BillurSamdancioglu Profile Picture

BillurSamdancioglu 239 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans