Hi All,
How can I set days cover in item coverage? eg: I want to have stock to cover 14 days cover of demand. Please see below for illustration
Current setup:
Coverage code: Period
Coverage period: 14
Positive days: 14
Reference | Requirement date | Req. Quantity | Accumulated
On hand | 19-Nov | 97 | 97
Demand forecast | 22 Nov | -50 | 47
Planned transfer | 29 Nov| 83 | 130
Demand forecast | 29 Nov | -60 | 70
Demand forecast | 6 Dec | -70 | 0
Planned transfer |13 Dec | 170 | 170
Demand forecast | 13 Dec | -80 | 90
Demand forecast | 20 Dec | -90 | 0
....
Question:
On 29 Nov planned transfer generated to cover future 2 weeks demand (29 Nov & 13 Dec). Problem is it generated every 14 days.
I expect to have another planned transfer on 6 Dec, to cover 6 Dec & 13 Dec demand (instead of waiting stock become 0 on 13 Dec) then another planned transfer on 13 Dec to cover 13 Dec & 20 Dec demand.
I already tried all of the coverage setting, but still cant find the correct one. Can someone help me with the setup to get what I expect?
Thanks in advance.