Hello Experts,
Kindly advise if the below scenario can be achieved in D365FO.
My client is looking for a way to move the cost from WIP A/c according to the % of revenue recognized during estimate process. Currently D365 moves all the costs that are booked in a project as on the estimate date.
Example:
Project contract amount is 187,500
Total cost and Booked cost is 100,000
POC 50% hence Accrued revenue is 93,750 but the system reversing entire cost of 100000 which leads to negative GP of 6.67%
Expected result is : Cost should be 50000 over revenue of 93750
Thanks in advance