Resource number is not specified. at Job Registration

Posted on by 529

Hi all,

I have many started productions right now (around 40 in total) each production has in avg 5 operations. Each operation is attached to only one resource (1:1) for Job Scheduling.

I have notice that sometimes for some productions. some operation are not being scheduled and the job scheduled being canceled.. You guys now why? what can I do to avoid that? what is the reason for a certain operation to be canceled from scheduling?

here some screen to picture the hole idea/configuration

I have been starting the same production many times, rescheduled the jobs but is the same. the resource is not being attached on the scheduling tab and is marked as canceled.

your help is greatly appreciated. thanks a lot for your time guys

143838880_2D00_45eb42e3_2D00_9275_2D00_4a84_2D00_afbd_2D00_427388460d3f.png143839097_2D00_c79469a3_2D00_2e33_2D00_4ca4_2D00_bebb_2D00_058588d39480.png143839554_2D00_f3d24848_2D00_7e28_2D00_46af_2D00_8784_2D00_c97cfeabce2c.png143839769_2D00_f0be5a83_2D00_18a3_2D00_441e_2D00_a378_2D00_320e2c0a00ea.png143840297_2D00_bf6dfb92_2D00_38af_2D00_486f_2D00_b2b4_2D00_770afbe42104.png143840494_2D00_f79cc330_2D00_fb4e_2D00_45fb_2D00_81be_2D00_e090c3bdb0c9.png

  • Suggested answer
    CBNestor Profile Picture
    CBNestor 529 on at
    RE: Resource number is not specified. at Job Registration

    [SOLVED]

    Production Control Parameter -> Journals -> Uncheck "Update capacity Plan"

    pastedimage1638446121843v1.png

  • CBNestor Profile Picture
    CBNestor 529 on at
    RE: Resource number is not specified. at Job Registration

    I've got to the source of the problem, (not yet the solution)

    1. Reset the production order to created

    2. started again, and all operations an working as spected.

    3. post a route card with 100% or more of the processing percentage.

    4. Synchronize the Job table on Production -> Periodic ->Synchronize job table.

    you will not be able to clock in more hours from the job Registration form because the Operation has been "completed" (run time has been reached).

  • CBNestor Profile Picture
    CBNestor 529 on at
    RE: Resource number is not specified. at Job Registration

    no. both are primary. I did not approve the route version since the change was made on the production not on the item

  • faiz7049 Profile Picture
    faiz7049 1,879 on at
    RE: Resource number is not specified. at Job Registration

    and also after added new operation. Did you approve Route version ?

    Thanks,

    Faiz

  • faiz7049 Profile Picture
    faiz7049 1,879 on at
    RE: Resource number is not specified. at Job Registration

    did you set priority to secondary . As I see that same operation in sequence.

    regards,

    Faiz

  • CBNestor Profile Picture
    CBNestor 529 on at
    RE: Resource number is not specified. at Job Registration

    Hi Faiz, thanks a lot for your reply

    pastedimage1638255220414v1.png

    I have all my resources set to the same calendar.

    I have added a new operation (No 5) with the same operation/resource as the one that is not working and re-scheduled the production. For the new is working and the old one is still the same. the only thing I noticed is that there is already time used in the feedback (0.14hrs) for that operation (No 10)

    pastedimage1638255761301v2.png

    your help is greatly appreciated

  • faiz7049 Profile Picture
    faiz7049 1,879 on at
    RE: Resource number is not specified. at Job Registration

    Hi Nestor,

    Kindly check the calender.

    Production Control  Route – Operation – Resources – Right click and or click View resource – Resource form – Resource groups – Calendar.

    Calender is associated with the resources and the working times are updated.

    Organization administration –>Calendars – >Calendars – 24 Hours– Working times and check the form is not empty or that the days don’t have Control set to Closed.

    Thanks,

    Faiz

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,269 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,198 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Product updates

Dynamics 365 release plans