Hi All,
What is Planning Level code in Prod.Order Component. This field always holds zero value. In some cases , this value changed to one at that time we can not pick this item. What is the significance of this value, while creating pick?
Regards,
Rasheed
*This post is locked for comments
How it affects inventory picking for a work order. If the value turn to one, work order picking not possible
Normally it's updated when you launch a replenishment plan.
Hi Stefano,
This field always holds the value 'Zero' but some time the value is changed to 'one' at that time system will not allow to pick that item. When this value changes from zero to One?
Regards,
Rasheed. K.R.
This field is used internally. The field indicates which planning level the item on the production order line belongs to. The program automatically fills in this field when it calculates a plan or refreshes a multilevel production order.
Sohail Ahmed
2
mmv
2
Amol Salvi