If a resource A is working on requirement-1 of a Project. This is a requirement for 4 hours.
I want to break this requirement and assign 2 hours to resource A and 2 hours to resource B in Schedule board.
Is it possible? Please suggest.
Yes this is possible. One of the easiest ways is to do this. Go to the schedule board. and click on the requirement you want to book. Then go to the resource you want to book and the day/time - click on that cell. You should then see on the right side of the schedule board, a Create Resource Booking form. Schedule with the proper booking method and # of hours. In your case, you want to set hours to 2. Then click book. That will leave the requirement down below with a remaining 2 hours to book. Let me know if you have any issues - I can record a video of it for you.