Hi 

I have created a working time calendar to account for the UK bank holidays and assigned it to 63 employees. I was under the impression this would automatically deduct these pre defined holiday days from the assigned employee's Leave allowance but it does not!?

Does anyone know how this should work? what am I missing?

pastedimage1617111031124v1.png

many thanks 

I have the same question (0)
  • Verified answer
    Parag Chapre Profile Picture
    12,254 Most Valuable Professional on at

    Hi Lucy,

    Did you enable the feature "Leave accrual holiday corrections"?

    Also, check the documentation from MS docs.

    docs.microsoft.com/.../hr-leave-and-absence-types

    Configure leave type rules

    Set rounding options for the leave type. Options include None, Up, Down, and Nearest. You can also set rounding precision for the leave type.

    Set Holiday correction for the leave type. When you select this option, Human Resources uses the number of holidays that fall on a work day to determine how to accrue time off for the leave type. For example, if Christmas Day falls on a Monday, Human Resources will subtract one day from the leave type when processing accruals.

    You set holidays in the working time calendar. For more information, see Create a working time calendar

  • Lucy0321 Profile Picture
    10 on at

    Hi Parag

    This has done it

    "Set Holiday correction for the leave type. When you select this option, Human Resources uses the number of holidays that fall on a work day to determine how to accrue time off for the leave type. For example, if Christmas Day falls on a Monday, Human Resources will subtract one day from the leave type when processing accruals."

    Thank you so much! I hadn't assigned it to a holiday plan

    Lucy

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 451 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 428 Super User 2025 Season 2

#3
BillurSamdancioglu Profile Picture

BillurSamdancioglu 239 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans