Does anyone have any ideas on why Master Planning would start throwing scheduling errors on end items that previously been working fine? I've got a client that started getting "not enough capacity could be found" feedback messages, resource group and resources appear fine, not using finite materials or capacity anywhere. When looking at the part routing, though, I notice route type is "standard", but when viewing the rout for the MP planned order it's showing up as "vendor" and it's definitely not an outsourced op.