In one of Project while adding new tasks via Schedule tab I am facing WBS ID error. I have already checked and as you can also see in below screen-shot they are not duplicated or blank also I am not trying to add task via any workflow or plugin. I am trying to add via User interface only.
Kindly help what can be done to fix this error.
Thanks & Regards,
Harshil Shah
Hi Harshil,
In PSA 3.x when you update task X, the system is displaying a message 'Syncing' above the Schedule/WBS.
Wait for the message to stop appearing before attempting another change of the same task.
This also applies to indenting and outdenting tasks.
I hope it helps.
Kind regards