Hi All,
This project has been going on for a few years. So it carries the original Line of Business 100. The new Account Structure does not have the Line of Business 100. If I invoice this project, it would not post because 100 is not included in the Account Structure (screenshot 2). Is there a way that I can tell the system that 100 is now 101 when I run the report to analyze the performances (profit, cost, resource, etc)? Is there a way to map LOB 100 = 101?
Or is there a way to allow posting LOB 100 strictly to a specific project?
If there is a simpler solution, please suggest it. I appreciated it very much!