Change and editable Created date and time in Update fast tab on Production Order

Posted on by 3,024

ProductionCreateddateandtime.png

Dear Experts,

There is any possibility to make "Created date and time" field in Update fast tab on production order    editable as estimated and started can be edit and  change it from the table, but the created date and time is extended data type please suggest .

Thanks and regards,

Shabir Ahmad

*This post is locked for comments

  • Suggested answer
    Satish Panwar Profile Picture
    Satish Panwar 14,645 on at
    RE: Change and editable Created date and time in Update fast tab on Production Order

    Hi Shabir,

    Understand the requirement from production department. You need to let them know that we can't change the created date as it is the date when the order was created (Once setup, no changes). If they don't like this behavior, they can always create another production order and delete existing one. This requirement has come up from some of our customers too, does come up during data migration but we don't modify / change created date. If you are not able to convince production department users, leverage hierarchy (IT) and avoid the change. If users are using created date for some other reason, a new field can always be added but it additional maintenance, reporting, customization etc.

    Please know that in AX2012, you may be able to find a way (customization in AX + SQL) to somehow update the created date time but it's not worth it and not the practice one should go for. Hope this helps.

    Thanks,

    Satish Panwar

    Please take time to click 'Yes' against the answers that help you guide in right direction to help other community members.

  • Shabir Ahmad Profile Picture
    Shabir Ahmad 3,024 on at
    RE: Change and editable Created date and time in Update fast tab on Production Order

    Sourav Dam,

    Thanks for your reply, sometimes, it is our need to change it.The requirement was given by production department to me, as i checked this field was extended data type and i was not able to make it editable or change it.

    Thanks and Regards,

    Shabir Ahmad

  • Suggested answer
    SouravDam Profile Picture
    SouravDam 11,721 on at
    RE: Change and editable Created date and time in Update fast tab on Production Order

    Hi Shabir Ahmad ,

    Let's discuss first; why this requirement is required to set this field editable.

    Are you facing any such cases where users are creating production orders in system and later just left it unused which is ultimately increasing number of documents in system but without any proper record ?

    Best regards,
    Sourav Dam

    Please take time to click 'Yes' against the answers that help you guide in right direction to help other community members.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,269 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,198 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans