Suggested Answer

Project budget balances - not showing consumed amounts correctly

(0) ShareShare
ReportReport
Posted on by 205

Project Budget Balances are not showing correct consumed budget

?When reviewing the Project Budget Balances screen, I discovered transactions that are correctly coded to this budget line are not showing as consumed costs. I'm wondering if this has something to do with the activities on the budget line item. Originally, the budget was set up with activities, however, since we are unable to get reports based on activities, we have stopped using them. I've included a screen shot of the journal entries that were used in the this particular scenario as well as some project reports showing where it is coded. How do we fix this so this area of the project module is more useful and so we can use this Project Budget Balances area to show real-time expenditures for each grant?

The path to this area is Project Mgnt & Accounting>Projects>All Projects>Subproject>Plan>Project>Project budget>Budget>Related information>Project budget balances.

pastedimage1659625117905v1.png

pastedimage1659625137849v2.png

pastedimage1659625168398v3.png

pastedimage1659625203745v4.png

pastedimage1659625227743v5.png

I have the same question (0)
  • Charlotte X Profile Picture
    on at

    Hi JamalK,

    Please wait for someone more experienced to answer this question.

    Best Regards,

    Charlotte

  • Vaibhav S Profile Picture
    240 on at

    Hi
    You able to solve this issue?
    I am also facing the same issue in D365FO.

    Please let me know

  • Suggested answer
    Gaurangkumar Jani Profile Picture
    4,534 User Group Leader on at

    Hi ASidd / Vaibhav S

    This is possible only if you have difference between level of budget available in Project and transaction posted, actually.

    Example, if you have created budget by activity and if you post a transaction without activity, the system can not provide consumption details it was consumed outside budget parameters.

    The same way if you post with activity, but you chose different categories, then also system can't provide consumption details as it's out of parameters of budget.

    Please let us know if this helps.

    Thanks,

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 551 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 450 Super User 2025 Season 2

#3
BillurSamdancioglu Profile Picture

BillurSamdancioglu 278 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans