Hello all,
I have configured a calendar template for 7.5 hours using a 'Generic' resource called 'Default Work Hours':

This resource has been applied to the 'Default Work Template' as 'Template Resource':

The 'Default Work Template' has been applied to all bookable resources in the system (using Set Calendar).
When creating a new project, the 'Default Work Template' is used as the 'Calendar Template', however when tasks are created in the project and duration set to 1 day, the task duration is 8 hours rather than 7.5 hours:

I can see that the calendar template is being respected as the finish has been pushed into the following day (changing the duration to 7.5 hours keeps the finish on the same day).
Does anyone know why the estimated effort is not 7.5 hours as defined in the calendar template?
This is throwing all project cost estimates, quote estimates and scheduling out as the effort on task is higher.