Hi all,
I hope someone can help me.A Resource Requirement has 40 hours to book for one Bookable resource.The Bookable resource has working hours from Monday to Friday for 8 hours a day.In the Schedule Board, I selected the Resource requirement, clicked the button Book, selected a Bookable Resource and made sure that the 40 hours are divided over 5 days, starting from Monday. I used Front load hours as a Booking method.
Now these 40 hours need to be rescheduled. Instead of starting on Monday, it needs to start on Wednesday.If I use the Move to (right click) option on the booking in the Weekly view, all 5 bookings are moved, but unfortunately the working hours of the Bookable Resource are not respected. Instead of Wednesday, Thursday, Friday, Monday and Tuesday, it plans in the weekend and does not respect the Working hours.
I get the same result doing this in the Daily view.
Is there a possibility or a workaround that I reschedule the 5 bookings at the same time and that the Working hours of the Bookable Resource is respected?