Hi all
I need some advice, I have a client that uses LOTS. They are a manufacturing company and ultimately moves all stock that will be consumed into a WIP Floor area. They want the system to auto pick the Lot number via Backflushing. I know this is not best practice, but they are trying to find ways to not have to go onto each consumption line to pick the lot number. Ideally they want to be able to go onto the order. Reserve the items which BC will do and it auto reserves the oldest lot in that WIP floor BIN, but they system STILL wants you to select the bin upon finishing the order.
Can anyone tell me if there is a way to auto allocate a lot to a consumption?
Best practice for me would be that they pick the consumption at the time of weighing out the products - they write down the lot numbers anyway. Perhaps I am just complicating things.
Hope to get some advice from other partners using lots in a manufacturing processing with warehouse management.
Debbie