Skip to main content

Notifications

Announcements

No record found.

Project Operations forum
Suggested answer

Issue with 9-hour workdays in Project Operations

Posted on by 5
I'm having a problem in Dynamics 365 Project Operations.  Our workday is 9 hours, I design the Resource calendars well with 9-hour days but when I create the TASKS in Project Operations grid with MS Project, it assumes 8 hour work days.   Has anyone had a similar situation and can help me?  Thanks in advance.
 
Tengo una dificultad en Dynamics 365 Project Operations.  Nuestra jornada laboral es de 9 horas, diseño bien los calendarios de los Recursos con jornadas de 9 horas pero cuando creo las TAREAS en cuadrícula de Project Operations con MS Project, asume jornadas laborales de 8 horas.   Alguien ha tenido una situación similar y me puede asistir?  Gracias adelantadas.
 
  • Erica J Ellis Profile Picture
    Erica J Ellis 60 on at
    Issue with 9-hour workdays in Project Operations
    The option to enable Self Defined Project Duration should be in the "Control de caracteristics" menu in the toolbar at the top of your screenshot. Do you see it there? If not, what version are you on?
  • Suggested answer
    AnProjOps Profile Picture
    AnProjOps 3 on at
    Issue with 9-hour workdays in Project Operations
    Hello,
     
    I agree with Erica that the self project duration can help you, however, you may experience issues since you are fixating the days of the month to 20 (example)
     
    You can also try to use the Project Calendar control feature with which you can directly see which calendar is being used for project scheduling. The first step would be to open the project and click on the Calendar tab, there you will see the working days for that specific project. If the work hours are not aligned to what you want, try to change the template using the Calendar action which is placed right next to the Project Budget. Here click Change template and select the one you want to use. After you perform these actions click again on the Calendar action and click Sync. With this function, the Tasks should get synced to the new calendar.
     
    Please let me know if this helped.
  • Suggested answer
    MI-27052137-0 Profile Picture
    MI-27052137-0 5 on at
    Issue with 9-hour workdays in Project Operations
    Hi Erica
     
    Thank you by your response.  But, I can't find the point that you have referenced: "Settings>Parameter, you can enable "Self Defined Project Duration" under Feature Control"
     
    Look next sreenshots althought my language is in spanish when I try to find:
     
    In my configuration can't find it... look:
     
     
    Can you tell me in what part I cand find the functionallity than you referenced?
     
    Thanks a lot in advance
  • Erica J Ellis Profile Picture
    Erica J Ellis 60 on at
    Issue with 9-hour workdays in Project Operations
    I think there is a new feature to help with this issue. If you go to Settings>Parameter, you can enable "Self Defined Project Duration" under Feature Control. It places a section on the Project like this - 

Helpful resources

Quick Links

First Dynamics 365 Community Call (CRM Edition)

Don't miss the first D365 Community Call on 7/10!

Community Spotlight of the Month

Kudos to Saurav Dhyani!

Congratulations to the June Top 10 community leaders!

These stars go above and beyond . . .

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 285,642 Super User

#2
Martin Dráb Profile Picture

Martin Dráb 225,485 Super User

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans