Attach Route Operations with specific Resource AX2012

(0) ShareShare
ReportReport
Posted on by 46

Hi All,

I want to set a 1-to-1 relation between an operation and a resource.

So every time a new route line for an item and/or production is added and I select an operation this operation will automatically set the related resource requirement.

this is what I tried to do:

Create an item code : All and set up the Resource requirement from there. but an error popsup after selecting the Resource (tip: the resources and operations have the same name)

pastedimage1619181658765v1.pngpastedimage1619181742228v2.png

Do you know what is going on? and how can I manage to set this up?

may thanks beforehand!

I have the same question (0)
  • André Arnaud de Calavon Profile Picture
    301,141 Super User 2025 Season 2 on at

    Hi Nestor,

    The error message is mentioning virtual companies. Have you shared tables via table collections and did setup virtual companies?

  • CBNestor Profile Picture
    46 on at

    Hi André,

    No idea about table collections and/or virtual companies. haven't touch that. I am just migrating data from one company to another (but just main tables, parameters and groups) trying to "make a copy" to build another legal entity. I dont know if that has something to do.

    But at least I haven't mess with virtual/table collections as far as I know? How to check/fix that?

  • CBNestor Profile Picture
    46 on at

    list of table collections

    pastedimage1619414168208v1.pngpastedimage1619414828370v1.png

  • Verified answer
    André Arnaud de Calavon Profile Picture
    301,141 Super User 2025 Season 2 on at

    Hi Nestor,

    The error might come due to missing related records. If you check the coding, it will try to get the company ID from some tables and if this is empty or part of a virtual company, this error is thrown. In your scenario, the company ID might be missing due to missing records.

    I would suggest to check if you need to copy data from the next tables as well:

    WrkCtrPCRouteOperationActivity

    WrkCtrProdRouteActivity

    WrkCtrProjForecastEmplActivity

    WrkCtrRouteOprActivity

  • Suggested answer
    CBNestor Profile Picture
    46 on at

    Hi André,

    After looking all tables related to RouteOpr I found out as you said some reference where missing.

    so I deleted all records with Item = "ALL" and Route= "ALL" and created back again by hand.

    So the references where populated from new a fresh by AX.

    now the operations are related 1-to-1 to the Resource  automatically as it should :)

    thanks for the help!

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 456 Super User 2025 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 429 Most Valuable Professional

#3
BillurSamdancioglu Profile Picture

BillurSamdancioglu 239 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans