Hi, what is the percentage calculation tied to the resource within a schedule board, and the other number as well?
@ThomasDayman is correct
the % is the resources used capacity for that day and the number in this instance is the hours booked per day for that week (or longer than a week based on your board settings
I believe the Percentage is the availability used up for that resource
example - A resource may have 8 hours for a work day. If you schedule a job for 8 hours then that resource will have 100% used capacity. If you schedule a job for 16 hours then the resource will have 200% capacity used.
The number to the left is how many hours the resource has been scheduled