I am drawing a blank and could use some guidance. I am working on intercompany master planning in D365 where company A sells to an end customer and buys from company B. The transport time from B to A is 42 days. The vendor LT in company B is 35 days.
When I run planning I would expect company A to have a planned order date of delivery date - 42 and company B would have a planned order date of company A order date -35. When using intercompany planned orders without auto-firming is there a way to show and respect the IC transport time between companies?
Thanks for any help you can provide
Dan