Editing Resource Assignment Hours

(1) ShareShare
ReportReport
Posted on by

Hi there,

I am playing around in our sandbox Project Operations environment to find some of the differences compared to our existing PSA environment. One thing I noticed, is that I cannot manually update the hours on the "Resource Assignment" tab within Project Operations, while I can manually update hours within PSA.

Anybody know how I can update this grid so I can spread out the hours more accurately instead of how it shows 39 hours for one day?

ResourceAssignmentHours.png

I have the same question (0)
  • Suggested answer
    apa Profile Picture
    8,284 Moderator on at

    jaydee23 this is a parity gap with PSA that is on the product team's backlog.

  • Community Member Profile Picture
    on at

    Hi Antti,

    So as of today, we cannot make edits into the Resource Assignment Hours directly in Project Operations, but this feature is on their backlog to include this as this feature is currently available in PSA?

  • Verified answer
    apa Profile Picture
    8,284 Moderator on at

    jaydee23 that's correct.

    A lot of the parity gaps have to do with schedulable tables and the way Project for the web works.

    docs.microsoft.com/.../schedule-api-preview

  • Community Member Profile Picture
    on at

    Thank you Antti! I am curious though, this link you provided (docs.microsoft.com/.../schedule-api-preview), where does it show the information about this feature being on the product backlog?

  • saraahammar Profile Picture
    5 on at
    [deleted]
  • JeffThorsen777 Profile Picture
    10 on at

    Thanks a lot!

  • KC-09050214-0 Profile Picture
    on at
    Brining this back up as a priority. I just implemented Project Operations and this is a big deal. I am surprised the Microsoft is saying that this product is ready for General Release without having the ability to assign hours to resources by task and edit those. This is a MAJOR gap!!!!  Please prioritize this.
  • JimA Profile Picture
    12 on at
    Morning all, I still dont see there is a solution to this challenge, other than adding separated tasks for each resource of course. Any other ideas out there?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 660 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 549 Super User 2025 Season 2

#3
Sohaib Cheema Profile Picture

Sohaib Cheema 307 User Group Leader

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans