Answered

Editing Resource Assignment Hours

Posted on by Microsoft Employee

Hi there,

I am playing around in our sandbox Project Operations environment to find some of the differences compared to our existing PSA environment. One thing I noticed, is that I cannot manually update the hours on the "Resource Assignment" tab within Project Operations, while I can manually update hours within PSA.

Anybody know how I can update this grid so I can spread out the hours more accurately instead of how it shows 39 hours for one day?

ResourceAssignmentHours.png

  • Editing Resource Assignment Hours
    Brining this back up as a priority. I just implemented Project Operations and this is a big deal. I am surprised the Microsoft is saying that this product is ready for General Release without having the ability to assign hours to resources by task and edit those. This is a MAJOR gap!!!!  Please prioritize this.
  • JeffThorsen777 Profile Picture
    JeffThorsen777 10 on at
    RE: Editing Resource Assignment Hours

    Thanks a lot!

  • saraahammar Profile Picture
    saraahammar 5 on at
    RE: Editing Resource Assignment Hours
    [deleted]
  • Community Member Profile Picture
    Community Member Microsoft Employee on at
    RE: Editing Resource Assignment Hours

    Thank you Antti! I am curious though, this link you provided (docs.microsoft.com/.../schedule-api-preview), where does it show the information about this feature being on the product backlog?

  • Verified answer
    apa Profile Picture
    apa 8,282 on at
    RE: Editing Resource Assignment Hours

    jaydee23 that's correct.

    A lot of the parity gaps have to do with schedulable tables and the way Project for the web works.

    docs.microsoft.com/.../schedule-api-preview

  • Community Member Profile Picture
    Community Member Microsoft Employee on at
    RE: Editing Resource Assignment Hours

    Hi Antti,

    So as of today, we cannot make edits into the Resource Assignment Hours directly in Project Operations, but this feature is on their backlog to include this as this feature is currently available in PSA?

  • Suggested answer
    apa Profile Picture
    apa 8,282 on at
    RE: Editing Resource Assignment Hours

    jaydee23 this is a parity gap with PSA that is on the product team's backlog.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,253 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,188 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Product updates

Dynamics 365 release plans