I have come across what I would consider an issue with how Master Planning is suggesting Actions be applied to Open Purchase Orders. Understanding that there are a lot of settings and parameters to cover, I will start with the issue to see if anyone else has seen this issue.
Consider this scenario:
I have 3 open purchase orders (PO101, PO102, and PO103)
Master Planning is suggesting that I advance PO103 in front of PO101 and PO102, then PO102 ahead of PO101, then push out PO101.
I would prefer that PO101 be advanced, then PO102, then push out PO103.
In other words, If today's date is 11/18/19:
PO101 - 1/1/2020 ~ Requested delivery date
PO102 - 2/1/2020 ~ Requested delivery date
PO103 - 3/1/2020 ~ Requested delivery date
AFTER MRP runs, the suggested delivery dates are as follows:
PO103 - 12/1/2019
PO102 - 1/1/2020
PO101 - 3/1/2020
I would prefer MRP to suggest dates as follows:
PO101 - 12/1/2019
PO102 - 1/1/2020
PO103 - 3/1/2020
Thanks!