web
You’re offline. This is a read only version of the page.
close
Skip to main content

Announcements

No record found.

News and Announcements icon
Community site session details

Community site session details

Session Id :
Finance | Project Operations, Human Resources, ...
Suggested Answer

Item calculated cost , Standard cost , weighted average

(0) ShareShare
ReportReport
Posted on by 227

Hello Experts,

We use weighted average for raw materials, and Standard cost for finish goods, we calculate the FG cost the system uses the standard price for RM defined in the item prices, is there any way the system can consider the running average (inventory cost price ) for the calculations ?

 

Another workaround could the system update the defined standard cost for RM as the running average.


in the way currently the system work, every time average change user has to enter the new average as RM standard cost otherwise we will have production price variances.

Thank you 

I have the same question (0)
  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Ahmad,

    If you plan doing such kind of cost price calculation and price updates then I would claim that you don't need standard costs.

    Why did you evaluate your FG with standard costs if this does not seem what you need?

    Best regards,

    Ludwig

  • Ahmad ghubj Profile Picture
    227 on at

    Hi Ludwig,

    We still need quantities variance, lotsize variance,..

    But regarding the raw material price we try at least to avoid as much as we can,

    It seems Microsoft will provide dual costing methodology functionality , as it was planned in 2020, but disappeared from the last release after they announced, if ever appear will solve such requirements that we nearly face in every manufacturing project

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Ahmad,

    Looks like that you really need standard costs and another valuation method in parallel.

    As far as I know there is something planned but not yet GA.

    Might be a good idea approaching the MS support team and ask whether and when this functionality will become available.

    Apart from that, I don't see much what you can do at the moment.

    (Recalculating your standard costs all the time will basically result in a current valuation method and won't help but not recalculating it seems not what you want/need)

    Best regards,

    Ludwig

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Giorgio Bonacorsi Profile Picture

Giorgio Bonacorsi 669

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 445 Super User 2026 Season 1

#3
Syed Haris Shah Profile Picture

Syed Haris Shah 331 Super User 2026 Season 1

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans