Suggested Answer

Item calculated cost , Standard cost , weighted average

(0) ShareShare
ReportReport
Posted on by 227

Hello Experts,

We use weighted average for raw materials, and Standard cost for finish goods, we calculate the FG cost the system uses the standard price for RM defined in the item prices, is there any way the system can consider the running average (inventory cost price ) for the calculations ?

 

Another workaround could the system update the defined standard cost for RM as the running average.


in the way currently the system work, every time average change user has to enter the new average as RM standard cost otherwise we will have production price variances.

Thank you 

I have the same question (0)
  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Ahmad,

    If you plan doing such kind of cost price calculation and price updates then I would claim that you don't need standard costs.

    Why did you evaluate your FG with standard costs if this does not seem what you need?

    Best regards,

    Ludwig

  • Ahmad ghubj  Profile Picture
    227 on at

    Hi Ludwig,

    We still need quantities variance, lotsize variance,..

    But regarding the raw material price we try at least to avoid as much as we can,

    It seems Microsoft will provide dual costing methodology functionality , as it was planned in 2020, but disappeared from the last release after they announced, if ever appear will solve such requirements that we nearly face in every manufacturing project

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Ahmad,

    Looks like that you really need standard costs and another valuation method in parallel.

    As far as I know there is something planned but not yet GA.

    Might be a good idea approaching the MS support team and ask whether and when this functionality will become available.

    Apart from that, I don't see much what you can do at the moment.

    (Recalculating your standard costs all the time will basically result in a current valuation method and won't help but not recalculating it seems not what you want/need)

    Best regards,

    Ludwig

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 451 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 428 Super User 2025 Season 2

#3
BillurSamdancioglu Profile Picture

BillurSamdancioglu 239 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans