Project Beginning Balance journal does not set the Billed-to-Date amount on project

Posted on by 93

We are using the Project Beginning balance journal to migrate projects from a legacy system for an acquisition.  After the invoice has posting we are seeing the posted transactions under the project and the project statement values look correct including the invoice tab, however the billed-to-date value is zero.  We expect that the beginning balance journal would set the value.

We are on Dynamics 365 version 10.0.29.  We've used the beginning balance journal for similar migrations in the past and it looks like we've never noticed it before.

We posted a $.01 invoice see if it would recalculate the billed-to-date, but it just shows the $.01.

Any ideas on how to correct or populate the billed-to-date for the beginning balance?

  • Project Beginning Balance journal does not set the Billed-to-Date amount on project
    Mark - did you ever get an answer? We are currently working on this exact same thing.

Helpful resources

Quick Links

Replay now available! Dynamics 365 Community Call (CRM Edition)

Catch up on the first D365 Community Call held on 7/10

Community Spotlight of the Month

Kudos to Saurav Dhyani!

Congratulations to the June Top 10 community leaders!

These stars go above and beyond . . .

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 287,696 Super User

#2
Martin Dráb Profile Picture

Martin Dráb 225,490 Super User

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans